Cottonwood Bayou Solar

EIA-860M planned generators: (TS) Construction complete, but not yet in commercial operation (as of 1 Aug 2026)

May be complete: the estimated completion (Sep 2026) has passed, and no newer source says so either way.

Stage
Under constructionreported Aug 2026
Value
Not published
Capacity
350 MW
Owner
Cottonwood Bayou Solar, LLC
Last checked
14 Nov 2026

Stage timeline

  1. ProposedNot reported
  2. ApprovedNot reported
  3. Under constructionreported Aug 2026
  4. CompleteNot yet

Facts

Type
Dams and power generation (solar) · Dams and power generation in Texas
Location
Brazoria County
Municipality
Brazoria County
Province or state
Texas, United States · All of the United States
Estimated completion
Sep 2026 from EIA-860M planned generators

Nearby projects

  • Willow Beach Wind · Dams and power generation · Proposed · about 12 km away
  • Rock N' Roll · Dams and power generation · Proposed · about 16 km away
  • Myrtle Solar, LLC · Dams and power generation · Under construction · about 17 km away
  • Brazoria Solar I · Dams and power generation · Under construction · about 18 km away
  • Red Egret · Dams and power generation · Under construction · about 30 km away

Latest updates

Stage history

  1. Under construction EIA-860M planned generators: (TS) Construction complete, but not yet in commercial operation (as of 1 Aug 2026)

Sources

Licences: US federal government work (public domain). Full credits: Data sources and licences.