Build Almanac

Menu

Show on map

Show Me State Solar

EIA-860M planned generators: (TS) Construction complete, but not yet in commercial operation (as of 1 Aug 2026)

May be complete: the estimated completion (Oct 2026) has passed, and no newer source says so either way.

Stage
Under constructionreported Aug 2026
Value
Not published
Capacity
250 MW
Owner
Show Me State Solar, LLC
Last checked
14 Nov 2026

Stage timeline

  1. ProposedNot reported
  2. ApprovedNot reported
  3. Under constructionreported Aug 2026
  4. CompleteNot yet

Facts

Type
Dams and power generation (solar) · Dams and power generation in Missouri
Location
Callaway County
Municipality
Callaway County
Province or state
Missouri, United States · All of the United States
Estimated completion
Oct 2026 from EIA-860M planned generators

Latest updates

Stage history

  1. Under construction EIA-860M planned generators: (TS) Construction complete, but not yet in commercial operation (as of 1 Aug 2026)

Sources

Licences: US federal government work (public domain). Full credits: Data sources and licences.

Something wrong or out of date? Report a correction.