Build Almanac

Menu

Show on map

Raccordement du complexe de La Romaine au réseau de transport

NRCan Major Projects Inventory: Under Construction (as of 1 Oct 2025)

Stage
Under constructionreported Oct 2025
Value
C$1.3Bfrom NRCan Major Projects Inventory
Capacity
Not published
Owner
Hydro-Québec
Last checked
1 Oct 2025

Stage timeline

  1. ProposedNot reported
  2. ApprovedNot reported
  3. Under constructionreported Oct 2025
  4. CompleteNot yet

Facts

Type
Transmission lines (line) · Transmission lines in Quebec
Location
Camp satellite line 34 5KV
Route
Approximate: the map joins the points the source gives with straight lines.
Municipality
Camp satellite line 34 5KV
Province or state
Quebec, Canada · All of Canada

Latest updates

Stage history

  1. Under construction NRCan Major Projects Inventory: Under Construction (as of 1 Oct 2025)

Sources

Licences: Open Government Licence – Canada. Full credits: Data sources and licences.

Something wrong or out of date? Report a correction.