Kemess Underground Copper-Gold Mine
BC Major Projects Inventory: Construction started
(as of 30 Sep 2025)
- Stage
- Under constructionreported 30 Sep 2025
- Value
- C$524Mfrom BC Major Projects Inventory
- Capacity
- Not published
- Owner
- Northgate Minerals Corp.
- Last checked
- 30 Sep 2025
Stage timeline
- ProposedNot reported
- ApprovedNot reported
- Under constructionreported 30 Sep 2025
- CompleteNot yet
Underground coal mine located 5 km north of the former Kemess South mine. Estimated annual mine production of 95,000 oz gold and 41.4 million lbs of copper over a 12-year mine life.
Facts
- Location
- Chetwynd
- Municipality
- Chetwynd
- Province or state
- British Columbia, Canada · All of Canada
Nearby projects
- Groundhog Project Anthracite Coal Mine · Mines · Proposed · about 92 km away
Latest updates
- : first recorded here. BC Major Projects Inventory, 30 Sep 2025 edition.
Stage history
- Under construction BC Major Projects Inventory:
Construction started
(as of 30 Sep 2025)
Sources
- BC Major Projects Inventory: MPI project 3043 (as of 30 Sep 2025)
Licences: Open Government Licence – British Columbia. Full credits: Data sources and licences.