Build Almanac

Menu

Show on map

Southern Bighorn Solar 2

EIA-860M planned generators: (L) Regulatory approvals pending. Not under construction (as of 1 Aug 2026)

Stage
Proposedreported Aug 2026
Value
Not published
Capacity
200 MW
Owner
425LM 8ME LLC
Last checked
14 Nov 2026

Stage timeline

  1. Proposedreported Aug 2026
  2. ApprovedNot yet
  3. Under constructionNot yet
  4. CompleteNot yet

Facts

Type
Dams and power generation (solar) · Dams and power generation in Nevada
Location
Clark County
Municipality
Clark County
Province or state
Nevada, United States · All of the United States
Estimated completion
Jul 2028 from EIA-860M planned generators

Nearby projects

Latest updates

Stage history

  1. Proposed EIA-860M planned generators: (L) Regulatory approvals pending. Not under construction (as of 1 Aug 2026)

Sources

Licences: US federal government work (public domain). Full credits: Data sources and licences.

Something wrong or out of date? Report a correction.