Jones City 1 Solar
EIA-860M planned generators: (TS) Construction complete, but not yet in commercial operation
(as of 1 Aug 2026)
May be complete: the estimated completion (Oct 2026) has passed, and no newer source says so either way.
- Stage
- Under constructionreported Aug 2026
- Value
- Not published
- Capacity
- 215 MW
- Last checked
- 14 Nov 2026
Stage timeline
- ProposedNot reported
- ApprovedNot reported
- Under constructionreported Aug 2026
- CompleteNot yet
Facts
- Location
- Jones County
- Municipality
- Jones County
- Province or state
- Texas, United States · All of the United States
- Estimated completion
- Oct 2026 from EIA-860M planned generators
Nearby projects
- Jones City 2 Solar · Dams and power generation · Under construction · about 2 km away
- Anson 2 Solar · Dams and power generation · Under construction · about 9 km away
- Tiger Solar · Dams and power generation · Under construction · about 12 km away
- Swenson Solar · Dams and power generation · Under construction · about 23 km away
- Funston Solar · Dams and power generation · Under construction · about 27 km away
Latest updates
- : first recorded here. EIA-860M planned generators, 1 Aug 2026 edition.
Stage history
- Under construction EIA-860M planned generators:
(TS) Construction complete, but not yet in commercial operation
(as of 1 Aug 2026)
Sources
- EIA-860M planned generators: EIA plant 66559 (as of 1 Aug 2026)
Licences: US federal government work (public domain). Full credits: Data sources and licences.
Something wrong or out of date? Report a correction.