Sanborn Hybrid 3
EIA-860M planned generators: (V) Under construction, more than 50 percent complete
(as of 1 Aug 2026)
- Stage
- Under constructionreported Aug 2026
- Value
- Not published
- Capacity
- 578 MW
- Owner
- Terra-Gen Operating Co-Hybrid
- Last checked
- 14 Nov 2026
Stage timeline
- ProposedNot reported
- ApprovedNot reported
- Under constructionreported Aug 2026
- CompleteNot yet
From space


2 × 2 km around the project's point, true colour. Contains modified Copernicus Sentinel data 2019, 2026.
Facts
- Location
- Kern County
- Municipality
- Kern County
- Province or state
- California, United States · All of the United States
- Estimated completion
- Dec 2026 from EIA-860M planned generators
Nearby projects
- Bellefield 2 Solar & Energy Storage Farm · Dams and power generation · Under construction · about 5 km away
- Aratina Solar Center 2 · Dams and power generation · Under construction · about 8 km away
- Big Creek Solar LLC · Dams and power generation · Under construction · about 19 km away
- SR 138 Northwest Corridor Improvement (I-5 to SR 14) · Highways and railroads · On hold · about 25 km away
- High Desert Corridor - New State Route 138 Project · Highways and railroads · On hold · about 46 km away
Latest updates
- : first recorded here. EIA-860M planned generators, 1 Aug 2026 edition.
Stage history
- Under construction EIA-860M planned generators:
(V) Under construction, more than 50 percent complete
(as of 1 Aug 2026)
Sources
- EIA-860M planned generators: EIA plant 69956 (as of 1 Aug 2026)
Licences: US federal government work (public domain); Copernicus Sentinel Data Legal Notice. Full credits: Data sources and licences.
Something wrong or out of date? Report a correction.