Sanborn Hybrid 3

EIA-860M planned generators: (V) Under construction, more than 50 percent complete (as of 1 Aug 2026)

Stage
Under constructionreported Aug 2026
Value
Not published
Capacity
578 MW
Owner
Terra-Gen Operating Co-Hybrid
Last checked
14 Nov 2026

Stage timeline

  1. ProposedNot reported
  2. ApprovedNot reported
  3. Under constructionreported Aug 2026
  4. CompleteNot yet

From space

Satellite view of the site, 2 by 2 km, Jul 2019
Jul 2019
Satellite view of the site, 2 by 2 km, Aug 2026
Aug 2026

2 × 2 km around the project's point, true colour. Contains modified Copernicus Sentinel data 2019, 2026.

Facts

Type
Dams and power generation (solar) · Dams and power generation in California
Location
Kern County
Municipality
Kern County
Province or state
California, United States · All of the United States
Estimated completion
Dec 2026 from EIA-860M planned generators

Nearby projects

Latest updates

Stage history

  1. Under construction EIA-860M planned generators: (V) Under construction, more than 50 percent complete (as of 1 Aug 2026)