Remplacement des transformateurs au poste de Saraguay, à la reconstruction d’une ligne souterraine Saraguay–Mont-Royal et à la construction du nouveau poste de Côte-Saint-Luc à 315-25 kV

NRCan Major Projects Inventory: In Review (as of 1 Oct 2025)

Approximate location: the source names only the municipality, so the map places this project at a point inside it (from Statistics Canada's census subdivisions), not at its site.

Stage
Proposedreported Oct 2025
Value
C$888Mfrom NRCan Major Projects Inventory
Capacity
Not published
Owner
Hydro-Québec
Last checked
1 Oct 2025

Stage timeline

  1. Proposedreported Oct 2025
  2. ApprovedNot yet
  3. Under constructionNot yet
  4. CompleteNot yet

Facts

Type
Transmission lines (line) · Transmission lines in Quebec
Location
Montréal (approximate location: placed at the municipality)
Municipality
Montréal
Province or state
Quebec, Canada · All of Canada

Nearby projects

Latest updates

Stage history

  1. Proposed NRCan Major Projects Inventory: In Review (as of 1 Oct 2025)