Build Almanac

Menu

Show on map

Horseshoe Lake

EIA-860M planned generators: (TS) Construction complete, but not yet in commercial operation (as of 1 Aug 2026)

Stage
Under constructionreported Aug 2026
Value
Not published
Capacity
896 MW
Owner
Oklahoma Gas & Electric Co
Last checked
14 Nov 2026

Stage timeline

  1. ProposedNot reported
  2. ApprovedNot reported
  3. Under constructionreported Aug 2026
  4. CompleteNot yet

From space

Satellite view of the site, 2 by 2 km, Jul 2019
Jul 2019
Satellite view of the site, 2 by 2 km, Jul 2026
Jul 2026

2 × 2 km around the project's point, true colour. Contains modified Copernicus Sentinel data 2019, 2026.

Facts

Type
Dams and power generation (gas) · Dams and power generation in Oklahoma
Location
Oklahoma County
Municipality
Oklahoma County
Province or state
Oklahoma, United States · All of the United States
Estimated completion
Feb 2029 from EIA-860M planned generators

Nearby projects

Latest updates

Stage history

  1. Under construction EIA-860M planned generators: (TS) Construction complete, but not yet in commercial operation (as of 1 Aug 2026)

Sources

Licences: US federal government work (public domain); Copernicus Sentinel Data Legal Notice. Full credits: Data sources and licences.

Something wrong or out of date? Report a correction.