Sturgeon County data center
Data-centre campus pages (hand-curated): Ground broken on 8 Jul 2026.
(as of 3 Nov 2026)
Approximate location: the source names only the municipality, so the map places this project at a point inside it (from Statistics Canada's census subdivisions), not at its site.
- Stage
- Under constructionreported 3 Nov 2026
- Value
- C$13Bfrom Data-centre campus pages (hand-curated)
- Capacity
- 1,000 MW power demand (campus total)
- Owner
- Meta
- Last checked
- 3 Nov 2026
Stage timeline
- ProposedNot reported
- ApprovedNot reported
- Under constructionreported 3 Nov 2026
- CompleteNot yet
Facts
- Type
- Data centres
- Location
- Sturgeon County (approximate location: placed at the municipality)
- Municipality
- Sturgeon County
- Province or state
- Alberta, Canada · All of Canada
Nearby projects
- NGL North System (Phase 2) · Pipelines, oil and gas · Under construction · under 1 km away (an approximate location)
- Greenlight Electricity Centre · Dams and power generation · Proposed · about 8 km away (an approximate location)
- Heartland Waste to Power Project · Large industrial plants · Approved · about 18 km away (an approximate location)
- ATCO Hydrogen Project · Large industrial plants · Proposed · about 20 km away (an approximate location)
- Linde Integrated Clean Hydrogen and Atmospheric Gases Facility · Large industrial plants · Under construction · about 20 km away (an approximate location)
Latest updates
- : first recorded here. Data-centre campus pages (hand-curated), 3 Nov 2026 edition.
Stage history
- Under construction Data-centre campus pages (hand-curated):
Ground broken on 8 Jul 2026.
(as of 3 Nov 2026)
Sources
- Data-centre campus pages (hand-curated): meta-sturgeon-county (as of 3 Nov 2026)
Licences: Open Government Licence – Canada. Full credits: Data sources and licences.
Something wrong or out of date? Report a correction.