Amador BESS

EIA-860M planned generators: (V) Under construction, more than 50 percent complete (as of 1 Aug 2026)

Stage
Under constructionreported Aug 2026
Value
Not published
Capacity
220 MW
Owner
BT Amador Storage LLC
Last checked
14 Nov 2026

Stage timeline

  1. ProposedNot reported
  2. ApprovedNot reported
  3. Under constructionreported Aug 2026
  4. CompleteNot yet

Facts

Type
Dams and power generation (energy storage) · Dams and power generation in Texas
Location
Van Zandt County
Municipality
Van Zandt County
Province or state
Texas, United States · All of the United States
Estimated completion
Apr 2027 from EIA-860M planned generators

Nearby projects

  • Elm Flats Solar · Dams and power generation · Under construction · about 48 km away
  • Amerada · Dams and power generation · Proposed · about 69 km away
  • Tehuacana Creek Solar · Dams and power generation · Under construction · about 72 km away
  • Mallard Energy Storage · Dams and power generation · Under construction · about 76 km away
  • I-30 East Corridor · Highways and railroads · Proposed · about 78 km away

Latest updates

Stage history

  1. Under construction EIA-860M planned generators: (V) Under construction, more than 50 percent complete (as of 1 Aug 2026)

Sources

Licences: US federal government work (public domain). Full credits: Data sources and licences.

Something wrong or out of date? Report a correction.