Delta Blues Advanced Power Station

EIA-860M planned generators: (L) Regulatory approvals pending. Not under construction (as of 1 Aug 2026)

Stage
Proposedreported Aug 2026
Value
Not published
Capacity
818.7 MW
Owner
Entergy Mississippi LLC
Last checked
14 Nov 2026

Stage timeline

  1. Proposedreported Aug 2026
  2. ApprovedNot yet
  3. Under constructionNot yet
  4. CompleteNot yet

Facts

Type
Dams and power generation (gas) · Dams and power generation in Mississippi
Location
Washington County
Municipality
Washington County
Province or state
Mississippi, United States · All of the United States
Estimated completion
May 2028 from EIA-860M planned generators

Nearby projects

  • Greer Solar Plant · Dams and power generation · Under construction · about 37 km away
  • Hwy 82 Improvements · Highways and railroads · Proposed · about 61 km away
  • Beekman Solar · Dams and power generation · Under construction · about 85 km away

Latest updates

Stage history

  1. Proposed EIA-860M planned generators: (L) Regulatory approvals pending. Not under construction (as of 1 Aug 2026)

Sources

Licences: US federal government work (public domain). Full credits: Data sources and licences.

Something wrong or out of date? Report a correction.