Revolution Wind

EIA-860M planned generators: (V) Under construction, more than 50 percent complete (as of 1 Aug 2026)

May be complete: the estimated completion (Nov 2026) has passed, and no newer source says so either way.

Stage
Under constructionreported Aug 2026
Value
Not published
Capacity
715 MW
Owner
Orsted Wind Power North America LLC
Last checked
14 Nov 2026

Stage timeline

  1. ProposedNot reported
  2. ApprovedNot reported
  3. Under constructionreported Aug 2026
  4. CompleteNot yet

From space

Satellite view of the site, 2 by 2 km, Jun 2019
Jun 2019
Satellite view of the site, 2 by 2 km, Jun 2026
Jun 2026

2 × 2 km around the project's point, true colour. Contains modified Copernicus Sentinel data 2019, 2026.

Facts

Type
Dams and power generation (wind) · Dams and power generation in the United States
Location
Washington County
Municipality
Washington County
Province or state
Rhode Island, United States · All of the United States
Estimated completion
Nov 2026 from EIA-860M planned generators

Nearby projects

  • Sunrise Wind · Dams and power generation · Under construction · about 20 km away
  • Beacon Wind · Dams and power generation · On hold · about 58 km away

Latest updates

Stage history

  1. Under construction EIA-860M planned generators: (V) Under construction, more than 50 percent complete (as of 1 Aug 2026)

Sources

Licences: US federal government work (public domain); Copernicus Sentinel Data Legal Notice. Full credits: Data sources and licences.

Something wrong or out of date? Report a correction.