GulfStar Power, LLC
EIA-860M planned generators: (TS) Construction complete, but not yet in commercial operation
(as of 1 Aug 2026)
May be complete: the estimated completion (Oct 2026) has passed, and no newer source says so either way.
- Stage
- Under constructionreported Aug 2026
- Value
- Not published
- Capacity
- 451.6 MW
- Owner
- GulfStar Power, LLC
- Last checked
- 14 Nov 2026
Stage timeline
- ProposedNot reported
- ApprovedNot reported
- Under constructionreported Aug 2026
- CompleteNot yet
Facts
- Location
- Wharton County
- Municipality
- Wharton County
- Province or state
- Texas, United States · All of the United States
- Estimated completion
- Oct 2026 from EIA-860M planned generators
Nearby projects
- OCI SunRoper · Dams and power generation · Proposed · about 7 km away
- Ventures BESS · Dams and power generation · Proposed · about 24 km away
- Castor · Dams and power generation · Under construction · about 31 km away
- Danish Fields Solar, LLC · Dams and power generation · Under construction · about 32 km away
- Rock Rose Energy Storage · Dams and power generation · Under construction · about 32 km away
Latest updates
- : first recorded here. EIA-860M planned generators, 1 Aug 2026 edition.
Stage history
- Under construction EIA-860M planned generators:
(TS) Construction complete, but not yet in commercial operation
(as of 1 Aug 2026)
Sources
- EIA-860M planned generators: EIA plant 66871 (as of 1 Aug 2026)
Licences: US federal government work (public domain). Full credits: Data sources and licences.