Kerr - Sulphurets - Mitchell (KSM) Gold/Copper
BC Major Projects Inventory: Construction started
(as of 30 Sep 2025)
- Stage
- Under constructionreported 30 Sep 2025
- Value
- C$8.4Bfrom BC Major Projects Inventory
- Capacity
- Not published
- Owner
- Seabridge Gold Inc.
- Last checked
- 30 Sep 2025
Stage timeline
- ProposedNot reported
- ApprovedNot reported
- Under constructionreported 30 Sep 2025
- CompleteNot yet
Open pit mine project, located approximately 65 km northwest of Stewart, consists of the copper porphyry deposits Kerr, Sulphurets, Mitchell and Iron Cap. Ore production of 80,000 to 120,000 mtpd over 25 years is expected, with 90,000 mtpd for the remainder of a 52 yr mine life.
Facts
- Location
- Stewart
- Municipality
- Stewart
- Province or state
- British Columbia, Canada · All of Canada
Nearby projects
- Eskay Creek Mine · Mines · Proposed · about 19 km away
- Snowfield Gold Project · Mines · On hold · about 32 km away
- Jade Lake Power Project · Dams and power generation · Proposed · about 43 km away (an approximate location)
- Treaty Creek Terminal - Transmission Load Interconnection (KSM) Project · Transmission lines · Under construction · about 43 km away (an approximate location)
- Premier Gold Project · Mines · Proposed · about 46 km away
Latest updates
- : first recorded here. BC Major Projects Inventory, 30 Sep 2025 edition.
Stage history
- Under construction BC Major Projects Inventory:
Construction started
(as of 30 Sep 2025)
Sources
- BC Major Projects Inventory: MPI project 2245 (as of 30 Sep 2025)
Licences: Open Government Licence – British Columbia. Full credits: Data sources and licences.
Something wrong or out of date? Report a correction.