Red Mountain Underground Gold Project
BC Major Projects Inventory: Proposed: Consultation/Approvals
(as of 30 Sep 2025)
- Stage
- Proposedreported 30 Sep 2025
- Value
- C$76Mfrom BC Major Projects Inventory
- Capacity
- Not published
- Owner
- Ascot Resources Ltd.
- Last checked
- 30 Sep 2025
Stage timeline
- Proposedreported 30 Sep 2025
- ApprovedNot yet
- Under constructionNot yet
- CompleteNot yet
Proposed underground gold mine located in the Bitter Creek Valley near Stewart. Mine life of 5 yrs is based on production estimate of 55,500 ounces gold and 171,000 ounces silver /yr. Project is certified under the Environmental Assessment Act.
Facts
- Location
- Stewart
- Municipality
- Stewart
- Province or state
- British Columbia, Canada · All of Canada
Nearby projects
- Premier Gold Project · Mines · Proposed · about 27 km away
- Jade Lake Power Project · Dams and power generation · Proposed · about 29 km away (an approximate location)
- Treaty Creek Terminal - Transmission Load Interconnection (KSM) Project · Transmission lines · Under construction · about 29 km away (an approximate location)
- Avanti Kitsault Mine Project · Mines · On hold · about 63 km away
- Kerr - Sulphurets - Mitchell (KSM) Gold/Copper · Mines · Under construction · about 69 km away
Latest updates
- : first recorded here. BC Major Projects Inventory, 30 Sep 2025 edition.
Stage history
- Proposed BC Major Projects Inventory:
Proposed: Consultation/Approvals
(as of 30 Sep 2025)
Sources
- BC Major Projects Inventory: MPI project 3590 (as of 30 Sep 2025)
Licences: Open Government Licence – British Columbia. Full credits: Data sources and licences.
Something wrong or out of date? Report a correction.